Research on curved block scheduling method in shipbuilding based on spatio-temporal constraint

Wang Mengying1, Jing Xuwen1, Zhou Honggen1, Li Lei1, Chen Xudong1, Shang Zhengyang2   

  1. 1 School of Mechanical Engineering,Jiangsu University of Science and Technology,Zhenjiang 212003,Jiangsu,China;
    2 School of Mechanical Engineering,Jiangsu University,Zhenjiang 212013,Jiangsu,China
  • Received:2015-12-15 Online:2017-09-20 Published:2018-01-09

Abstract: The scheduling problem of ship curved block has complex process and characteristic of spatio-temporal coupling,the lack of standard process and efficient method in formulating scheduling plan is bottleneck problem in shipbuilding.Proposed a scheduling method based on spatio-temporal constraint,it first build mathematical model contains spatio-temporal constraint,then use rules and decomposed strategy to design a reasonable and simple heuristic algorithm,finally,some curved blocks were simulated as example to validate the scheduling method.The result shows that the scheduling method which proposed performs well and can bring dramatic increase in block production efficiency and utility rate of work space.

Key words: ship building, curved block, scheduling algorithm, spatio-temporal constraint